Expanded tolling on SR 520 to pay for project may be coming

Feb 29, 2024, 6:06 PM | Updated: 6:17 pm

Image: SR 520 bridge construction work continues. Expanded tolling on SR 520 may be coming....

SR 520 bridge construction work continues. Expanded tolling on SR 520 may be coming. (Photo: Chris Sullivan, 成人X站 Newsradio)

(Photo: Chris Sullivan, 成人X站 Newsradio)

There isn’t enough money in the budget to finish the State Route 520 (SR 520) project so the may expand tolling to make up the difference.

Estimates to build the final section of SR 520, between Montlake and Interstate 5 (I-5), are running 70% over budget. The legislature needs to find at least $560 million to fill the gap.

A bipartisan bill, , would expand tolling to help fill that gap. Right now, tolling is only allowed on the floating section of SR 520. The bill would remove that limit and expand the ability to toll drivers from I-5 in Seattle to the end of the line in Redmond. (A PDF of the substitute bill can be viewed .)

It would also allow the state to defer tax costs for construction.

The bill has passed the Senate and is moving quickly through the House. , D-Seattle, and , R-Yakima, co-sponsored the bill.

It would take effect 90 days after the session, though implementation would have to wait for new tolling equipment to be installed. A tolling and revenue study would also be completed before implementation.

Support for expanded tolling on SR 520

According to the Senate Bill Report, the (WSTC) is supportive of the bill and wants to work with the (WSDOT) on potential impacts through that study. (A PDF of the Senate Bill Report can be viewed .)

The report also states member outreach with residents impacted by the West End project showed “some would be OK with paying tolls to finish the project.”

Previous tolling scenario reports evaluated possible tolling in multiple locations in the corridor and otherwise.

The bill report also states the current West End project is “important for mobility and safety.”

“Numerous residents rely on the corridor for work purposes,” the report continues. “A delay on the project will cost taxpayers more on an already vulnerable bridge. The project will connect active transportation users to multiple areas.”

Contributing: Steve Coogan, MyNorthwest

Check out more of Chris’ Chokepoints here. You can also follow Chris on . to follow 成人X站 Newsradio Traffic’s profile .

Chokepoints

SB I-5 semi-truck collision...

Jason Sutich

All lanes back open on SB I-5 after 3 semitrucks collide

All lanes are back open on southbound I-5 at 54th Avenue in Fife after three semitrucks collided.

1 day ago

southbound I-405 toll...

Jason Sutich

WSDOT investigates glitch as I-405 toll signs show ‘FREE’

The express toll lanes on southbound I-405 between Lynnwood and Bellevue were free Thursday morning due to incorrect signage labeling the lanes as "FREE."

2 days ago

Washington speed infractions...

Jason Sutich

Work zone speed cameras catch thousands of drivers in first 90 days

The Washington State Patrol has issued 7,599 infractions for drivers speeding in road work zones across the state in the last 90 days, according to 成人X站 7.

2 days ago

Sound Transit light rail...

Chris Sullivan

Sound Transit eyes march to Everett

Sound Transit is looking to extend light rail service to Everett.

2 days ago

Northgate rollover crash...

MyNorthwest Staff

Busy intersection in Northgate back open after rollover crash

An intersection in Northgate is back open after a rollover crash.

3 days ago

Diverging Diamond Interchange...

Chris Sullivan

New interchange is open but westbound I-90 traffic likely won’t improve for months

The state's new Diverging Diamond Interchange (DDI) at SR 18 is now open and will hopefully improve traffic and safety.

4 days ago

Expanded tolling on SR 520 to pay for project may be coming