Two years from completion, Lynnwood Link construction reaches halfway point
Nov 24, 2021, 5:00 PM | Updated: Nov 26, 2021, 6:19 am

(Photo courtesy of Sound Transit via Flickr)
(Photo courtesy of Sound Transit via Flickr)
More than doubling the Puget Sound region鈥檚 light rail infrastructure, Sound Transit reports that it is set to meet its scheduled 2024 opening date for the Link extension into Lynnwood.
Finished or nearly complete aspects of the monumental construction project include all 188 columns, the majority of the framework鈥檚 533 girders, and 10 bridges.
鈥淭he remarkable progress we鈥檙e making is visible daily for anyone driving along I-5,鈥 wrote Sound Transit CEO Peter Rogoff in a news release. 鈥淐onsidering that most of the work to date has been done during the pandemic, this milestone is a testament to the commitment of the project鈥檚 workforce.鈥
Light rail to Lynnwood just passed the halfway mark! Twenty-minute trips to
roll in three years! Read all about it and check out the latest progress pics:鈥 Sound Transit #VaccinateWA – 馃殕 馃殘 馃殟 (@SoundTransit)
The project benefits from an abundance of federal funding — $1.17 billion of the total $3.1 billion project cost has been sponsored by the Federal Transit Administration under a Full Funding Grant Agreement with Sound Transit. The U.S. Department of Transportation鈥檚 Build America Bureau has also put up $658 million in low interest loans.
Sound Transit reports that the federal support has saved the regional taxpayers an estimated $200-300 million through low interest loans. DOT refinanced the loan in 2021 to take advantage of lower federal interest rates, saving a subsequent $150-250 million.
鈥淪nohomish County has been leading the way to ensure our residents get light rail as quickly as possible while staying within the budget,鈥 said Dave Somers, Sound Transit board member and Snohomish County executive. 鈥淎s Link Light Rail stretches north toward Everett, it will serve even more residents and provide more commuting options.鈥
Northgate light rail station opens as Sound Transit forges ahead on expansion
The transit agency is also set to open a supplemental parking garage at Lynnwood Transit Center by spring 2023. The garage will contain capacity for 1,679 vehicles in a five-story structure.
Upon completion in 2024, Lynnwood commuters will be able to reach the University of Washington in Seattle in 20 minutes, downtown Seattle in 27 minutes, and Sea-Tac Airport in an hour. Trains from Lynnwood to downtown Bellevue will reach their destination in an estimated 51 minutes.
The East Link鈥檚 14 miles of track along the I-90 bridge will connect Seattle through Bellevue into Redmond by 2023. Sound Transit recently finished construction on its parking garage at the future East Link South Bellevue Station.
鈥淚n just two years, riders will be able to avoid some of the worst highway congestion in the nation and enjoy reliable trips to their destination,鈥 said Paul Roberts, Sound Transit vice chair and Everett City Council member. 鈥淏ecause Sound Transit is at the national forefront of operating carbon-free transit, riding Lynnwood Link will be the environmentally friendly way to get around the region.鈥