Night closures of I-90 expected in Bellevue this week for light rail work
Apr 1, 2019, 2:06 PM | Updated: Apr 3, 2019, 6:01 pm

(Sound Transit)
(Sound Transit)
Crews working on the East Link light rail line will shut down portions of I-90 in Bellevue over the coming week. It began with a full closure of westbound traffic Monday night.
is shutting down portions of I-90 for crews to remove a crane that has been constructing the light rail . In order to do that, traffic needs to be halted. Crews will also take advantage of the closure to get additional work on the bridge done.
RELATED: East link project hits 30 percent mark
RELATED: Bellevue light rail tunnel hits milestone
If weather interferes with plans, additional closures could be needed.
Monday night/Tuesday morning: I-90 between I-405 and Bellevue Way SE was fully closed from 11 p.m. Monday until 5 a.m. Tuesday.
Tuesday night/Wednesday morning: Three left lanes of westbound I-90 were closed, as well as the HOV ramp from I-405 south to westbound I-90. One westbound lane remained open.
Wednesday night/Tuesday morning: Three lanes of westbound I-90 will be closed. Ramps will close from Bellevue Way SE to westbound I-90; I-405 to westbound I-90; and Richards Road to westbound I-90.
Thursday night/Friday morning: Two right lanes of westbound I-90 will be closed. Also, the ramp from Bellevue Way SE to westbound I-90 will be shut down.